|
Ecology home >
Solid Waste >
Industrial >
Aluminum Facilities
> Alcoa Vancouver Site
Alcoa Vancouver Site
SITE UPDATE (December 16, 2008)
East Landfill
Ecology is still actively negotiating a cleanup strategy with Alcoa to address the TCE contamination in the groundwater beneath
the landfill. The current negotiations are focused on a Consent Decree amendment and Cleanup Action Plan for the East Landfill.
When an agreement is reached, the public will be invited to comment on the proposal.
Columbia River Work
In late November 2008, the Army Corps of Engineers approved Alcoa’s permit application to work in the Columbia River. Alcoa began
dredging contaminated sediments on December 1, 2008. Within the first week, the majority of high level PCB-contaminated sediment was
removed. Alcoa began removing contaminated sediment from the clam beds the week of December 4. Dredging of low level PCB-contaminated
sediment will continue into January 2009.
Water quality monitoring downstream from the dredge project shows the project is within the turbidity standard established for this project.
Upland soil removal and bank stabilization work is proceeding along the river bank in front of the dredged areas. All of the upland
aluminum manufacturing and fabrication buildings have been removed. Demolition of the ore storage silos that remain along the Columbia
River will occur in early 2009 unless the Port of Vancouver requests that the silos remain on the site.
The river cleanup addresses: 1) PCB-impacted sediments found in the Columbia River, 2) petroleum impacted soils found in buried lagoons
called the Crowley Parcel, 3) petroleum impacted soils found near four underground storage tanks on the river dike, and 4) PCB impacted soils
found in an area known as the Soluble Oil Area on the east side of the Site.
You can find copies of the documents at these locations:
- Fort Vancouver Regional Library, 1007 East Mill Plain Blvd, Vancouver, WA
- Department of Ecology, 300 Desmond Drive, Lacey, WA
- Click here to read:
Draft RI/FS RI/FS Appendices and Figures, and Draft CAP (ftp)
Proposed Consent Decree
SEPA checklist
Consent Decree DNS
Please be aware that RI/FS Appendix G is over 600 MB. To download the Draft RI/FS, its Appendices and Figures, and Draft CAP ftp zip
files, click on the link above then:
- Double click on the files labeled "Alcoa Vancouver RIFS.zip", “RIFS Appendices A-B.zip”,
“RIFS Appendices C-I (no G).zip”, “RIFS Appendix G – WARNING – LARGE FILE.zip”, “RIFS Figures.zip” and
"Alcoa Vancouver CAP.zip"
- Click “Save as”
- Choose the location on your computer to save it to
- Click Save
- Go to the location on your computer you chose to save the file to
- Double click on the file
SITE HISTORY AND CLEANUP ACTIONS TO 2007
The Alcoa Vancouver site is located in Clark County on the north bank of the Columbia River approximately three miles northwest of downtown Vancouver, Washington. Alcoa constructed an aluminum smelter on the western portion of the site in 1940. Between 1944 and 1970, a number of fabrication operations were added to the facility to form aluminum into finished goods such as wire, rod, and extrusions. Alcoa operated the entire facility for approximately 45 years, until its closure in 1985.
In 1985, Alcoa sold the aluminum smelter to VANALCO. VANALCO has since been sold to Evergreen Aluminum (Glencore). While Alcoa has sold or discontinued all operations and divested much of the smelter property, the company has retained ownership of certain parcels, including the dock and alumina unloading facilities. Industrial and solid wastes from construction and operation of the aluminum smelter were stored in waste piles and consolidated in landfills onsite over the years. Hazardous contaminants in these wastes include petroleum hydrocarbons, polychlorinated biphenyls (PCBs), cyanide, fluoride, trichloroethylene (TCE), low-level organic chemicals, and metals.
Since 1990, Ecology has worked with Alcoa to determine the nature and extent of contamination within and resulting from the operation of the waste piles and landfills. An extensive investigation consisting of soil and groundwater monitoring was performed at the site. Feasibility studies were conducted to determine the best cleanup option for each waste pile, landfill, or other sub-site.
Evergreen Aluminum worked with Ecology in 2007 and 2008 to characterize and clean up the smelter portion of the Site. Evergreen
has since completed the removal of approximately 62,500 tons of contaminated soil and waste to an off-site landfill.
To date, Alcoa has spent approximately $42 million on cleanup at the Vancouver site, including $34 million on cleanup of PCBs.
PCB Cleanup and Source Control Actions to Date
| 1988 | Alcoa completes voluntary cleanup of hydraulic oil & PCB-contaminated soils
adjacent to Rod Mill
| | 1995 | Alcoa removes PCB-contaminated soil & concrete from
Rod Mill building
| | 1997 | Ecology issues Agreed Order to Alcoa to clean up
Northeast Landfill
Alcoa completes removal of waste from Northeast Landfill.
High level PCBs sent off-site. Low level PCBs consolidated in East Landfill
Ecology is notified that Clark County discovered PCBs in Columbia River
| | 1998 |
Ecology requires Alcoa to sample soils adjacent to East Landfill & on adjacent
river bank. PCBs discovered in river bank just downstream of landfill
Alcoa
applies to Corps of Engineers for Joint Aquatic Resource Permit to remove
PCB-contaminated soils from the south bank area of concern
| | 1999 | Ecology requires
Alcoa to conduct PCB sampling in Columbia River
| | 2000 | Alcoa completes phase I
river sampling & submits report to Ecology
| | 2001 | Alcoa completes Phase II river
sampling & submits report to Ecology
| | 2002 | Alcoa completes engineering design for
the East Landfill cap, south bank excavation & shoreline embankment; receives
aquatic resource permit
| | 2003 | Ecology issues
Interim Action Agreed Order to cap
East Landfill, excavate PCBs from south bank, & construct shoreline embankment
to prevent release of PCBs to river Excavation of south bank PCBs is completed;
area is back-filled with clean material
| | 2004 | Alcoa completes capping of East Landfill & construction of adjacent shoreline
embankment
| | 2005 | Alcoa completes additional design work to further stabilize embankment of the East Landfill and completes in water habitat restoration required by state resource agency.
| | 2006 | Alcoa installs rip rap to stabilize at the lower portion of East Landfill shoreline
embankment
| | 2007 | Ecology starts negotiations on Consent Decree for cleanup of Evergreen
(site
info) and Alcoa property
Ecology learns of PCB-contaminated clams in Columbia River adjacent to
Alcoa property
Department of Health issues health advisory prohibiting clam harvesting
on Columbia River near Alcoa property
Ecology assigns sediment & toxicology specialists & attorney to work
on Alcoa cleanup
Contaminated clam warming signs in 8 languages placed at boat launches
Ecology holds public meeting to discuss cleanup actions to date at
Evergreen & Alcoa properties. Ecology reviews progress of cleanup at
Crowley site
Alcoa posts additional clam warning signs on the smelter river bank
Ecology reviews risk data to determine final sediment cleanup standards and
action levels
Alcoa & Ecology agree on, and announce, an accelerated cleanup
schedule to complete site cleanup as soon as legally possible
|
| 2008 |
Alcoa submits application to Army Corps. of Engineers for permit to work in the Columbia River
Ecology issues an Order to begin upland work along Columbia River bank
Alcoa begins demolition of Rod Mill/Wire Mill/Extrusion Mill Buildling |
Other Site Cleanup Actions to Date
|
1986 | Ecology issues administrative order to conduct a clean up investigation and feasibility study for cleanup of spent potliner at Vancouver smelter
| | 1988 | Ecology directs Alcoa to supply fresh water to workers in response to trichloroethylene contamination in plant production well
| | 1990 | Ecology issues Agreed Order to determine source of TCE in drinking water
| | 1992 | Ecology issues Consent Decree for cleanup of spent potliner site. Waste removed & site capped by December
| | 1994 | Alcoa removes sludge from process water settling lagoon & constructs new lined lagoons
| | 1996 | Alcoa completes excavation & soil bioremediation of former hydraulic oil disposal site and contaminated soils adjacent to Extrusion Mill & present day power plant
| | 2007 | Ecology issues order to Evergreen Aluminum to characterize the aluminum production area of the Site. Evergreen conducts investigative sampling and begins demolition of smelter and cleanup
| | 2008 | Evergreen Aluminum completes cleanup of aluminum production area of the smelter property. Approximately 62,500 tons of contaminated soil and industrial waste is removed from Site to an off-site landfill. All aluminum production buildings are removed from the Site
|
Related Information
Additional Resources
|
|
SITE INFORMATION
Facility Site ID:
#21
Location:
Vancouver, Clark County
Contact:
Paul Skyllingstad, project manager
(360) 407-6949
Status:
Active
ADDITIONAL INFO
Alcoa Joint Aquatic Resources Permit Applications (JARPA) (pdf)
Alcoa Vancouver Focus Sheet (pdf)
Progress Report (html)
Final Enforcement Order (pdf)
Updated schedule in process
SITE NEWS
Alcoa News Releases:
12/16/2008 - Dredging underway at former Alcoa aluminum smelter
Ecology News Releases:
9/10/2008 - Agreement on consent decree reached; public comment period underway
6/5/2008 - Prep work for river sediment cleanup at Alcoa subject of meeting
2/15/2008 - Alcoa submits federal application for environmental dredging at Vancouver site
12/06/2007 - Agreement reached on river cleanup strategy for Vancouver's Alcoa site
11/09/2007 - Ecology, Alcoa announce accelerated cleanup of Vancouver site
Media Contact:
Kim Schmanke, Ecology communications
(360) 407-6239
|