Alcoa Vancouver Site

SITE UPDATE (December 16, 2008)

East Landfill

Ecology is still actively negotiating a cleanup strategy with Alcoa to address the TCE contamination in the groundwater beneath the landfill. The current negotiations are focused on a Consent Decree amendment and Cleanup Action Plan for the East Landfill. When an agreement is reached, the public will be invited to comment on the proposal.

Columbia River Work

In late November 2008, the Army Corps of Engineers approved Alcoa’s permit application to work in the Columbia River. Alcoa began dredging contaminated sediments on December 1, 2008. Within the first week, the majority of high level PCB-contaminated sediment was removed. Alcoa began removing contaminated sediment from the clam beds the week of December 4. Dredging of low level PCB-contaminated sediment will continue into January 2009.

Water quality monitoring downstream from the dredge project shows the project is within the turbidity standard established for this project.

Upland soil removal and bank stabilization work is proceeding along the river bank in front of the dredged areas. All of the upland aluminum manufacturing and fabrication buildings have been removed. Demolition of the ore storage silos that remain along the Columbia River will occur in early 2009 unless the Port of Vancouver requests that the silos remain on the site.

The river cleanup addresses: 1) PCB-impacted sediments found in the Columbia River, 2) petroleum impacted soils found in buried lagoons called the Crowley Parcel, 3) petroleum impacted soils found near four underground storage tanks on the river dike, and 4) PCB impacted soils found in an area known as the Soluble Oil Area on the east side of the Site.

You can find copies of the documents at these locations:

  • Fort Vancouver Regional Library, 1007 East Mill Plain Blvd, Vancouver, WA
  • Department of Ecology, 300 Desmond Drive, Lacey, WA
  • Click here to read:
Draft RI/FS RI/FS Appendices and Figures, and Draft CAP (ftp)
Proposed Consent Decree
SEPA checklist
Consent Decree DNS

Please be aware that RI/FS Appendix G is over 600 MB. To download the Draft RI/FS, its Appendices and Figures, and Draft CAP ftp zip files, click on the link above then:

  1. Double click on the files labeled "Alcoa Vancouver RIFS.zip", “RIFS Appendices A-B.zip”, “RIFS Appendices C-I (no G).zip”, “RIFS Appendix G – WARNING – LARGE FILE.zip”, “RIFS Figures.zip” and "Alcoa Vancouver CAP.zip"
  2. Click “Save as”
  3. Choose the location on your computer to save it to
  4. Click Save
  5. Go to the location on your computer you chose to save the file to
  6. Double click on the file

SITE HISTORY AND CLEANUP ACTIONS TO 2007

The Alcoa Vancouver site is located in Clark County on the north bank of the Columbia River approximately three miles northwest of downtown Vancouver, Washington. Alcoa constructed an aluminum smelter on the western portion of the site in 1940. Between 1944 and 1970, a number of fabrication operations were added to the facility to form aluminum into finished goods such as wire, rod, and extrusions. Alcoa operated the entire facility for approximately 45 years, until its closure in 1985.

In 1985, Alcoa sold the aluminum smelter to VANALCO. VANALCO has since been sold to Evergreen Aluminum (Glencore). While Alcoa has sold or discontinued all operations and divested much of the smelter property, the company has retained ownership of certain parcels, including the dock and alumina unloading facilities. Industrial and solid wastes from construction and operation of the aluminum smelter were stored in waste piles and consolidated in landfills onsite over the years. Hazardous contaminants in these wastes include petroleum hydrocarbons, polychlorinated biphenyls (PCBs), cyanide, fluoride, trichloroethylene (TCE), low-level organic chemicals, and metals.

Since 1990, Ecology has worked with Alcoa to determine the nature and extent of contamination within and resulting from the operation of the waste piles and landfills. An extensive investigation consisting of soil and groundwater monitoring was performed at the site. Feasibility studies were conducted to determine the best cleanup option for each waste pile, landfill, or other sub-site.

Evergreen Aluminum worked with Ecology in 2007 and 2008 to characterize and clean up the smelter portion of the Site. Evergreen has since completed the removal of approximately 62,500 tons of contaminated soil and waste to an off-site landfill.

To date, Alcoa has spent approximately $42 million on cleanup at the Vancouver site, including $34 million on cleanup of PCBs.

PCB Cleanup and Source Control Actions to Date

1988 Alcoa completes voluntary cleanup of hydraulic oil & PCB-contaminated soils adjacent to Rod Mill
1995 Alcoa removes PCB-contaminated soil & concrete from Rod Mill building
1997 Ecology issues Agreed Order to Alcoa to clean up Northeast Landfill

Alcoa completes removal of waste from Northeast Landfill. High level PCBs sent off-site. Low level PCBs consolidated in East Landfill

Ecology is notified that Clark County discovered PCBs in Columbia River

1998 Ecology requires Alcoa to sample soils adjacent to East Landfill & on adjacent river bank. PCBs discovered in river bank just downstream of landfill

Alcoa applies to Corps of Engineers for Joint Aquatic Resource Permit to remove PCB-contaminated soils from the south bank area of concern

1999 Ecology requires Alcoa to conduct PCB sampling in Columbia River
2000 Alcoa completes phase I river sampling & submits report to Ecology
2001 Alcoa completes Phase II river sampling & submits report to Ecology
2002 Alcoa completes engineering design for the East Landfill cap, south bank excavation & shoreline embankment; receives aquatic resource permit
2003 Ecology issues Interim Action Agreed Order to cap East Landfill, excavate PCBs from south bank, & construct shoreline embankment to prevent release of PCBs to river

Excavation of south bank PCBs is completed; area is back-filled with clean material

2004 Alcoa completes capping of East Landfill & construction of adjacent shoreline embankment
2005 Alcoa completes additional design work to further stabilize embankment of the East Landfill and completes in water habitat restoration required by state resource agency.
2006 Alcoa installs rip rap to stabilize at the lower portion of East Landfill shoreline embankment
2007 Ecology starts negotiations on Consent Decree for cleanup of Evergreen (site info) and Alcoa property

Ecology learns of PCB-contaminated clams in Columbia River adjacent to Alcoa property

Department of Health issues health advisory prohibiting clam harvesting on Columbia River near Alcoa property

Ecology assigns sediment & toxicology specialists & attorney to work on Alcoa cleanup

Contaminated clam warming signs in 8 languages placed at boat launches

Ecology holds public meeting to discuss cleanup actions to date at Evergreen & Alcoa properties. Ecology reviews progress of cleanup at Crowley site

Alcoa posts additional clam warning signs on the smelter river bank

Ecology reviews risk data to determine final sediment cleanup standards and action levels

Alcoa & Ecology agree on, and announce, an accelerated cleanup schedule to complete site cleanup as soon as legally possible

2008 Alcoa submits application to Army Corps. of Engineers for permit to work in the Columbia River

Ecology issues an Order to begin upland work along Columbia River bank

Alcoa begins demolition of Rod Mill/Wire Mill/Extrusion Mill Buildling

Other Site Cleanup Actions to Date

1986 Ecology issues administrative order to conduct a clean up investigation and feasibility study for cleanup of spent potliner at Vancouver smelter
1988 Ecology directs Alcoa to supply fresh water to workers in response to trichloroethylene contamination in plant production well
1990 Ecology issues Agreed Order to determine source of TCE in drinking water
1992 Ecology issues Consent Decree for cleanup of spent potliner site. Waste removed & site capped by December
1994 Alcoa removes sludge from process water settling lagoon & constructs new lined lagoons
1996 Alcoa completes excavation & soil bioremediation of former hydraulic oil disposal site and contaminated soils adjacent to Extrusion Mill & present day power plant
2007 Ecology issues order to Evergreen Aluminum to characterize the aluminum production area of the Site. Evergreen conducts investigative sampling and begins demolition of smelter and cleanup
2008 Evergreen Aluminum completes cleanup of aluminum production area of the smelter property. Approximately 62,500 tons of contaminated soil and industrial waste is removed from Site to an off-site landfill. All aluminum production buildings are removed from the Site

Related Information

Additional Resources

 

 

map showing site location as Clark county, WA SITE INFORMATION

Facility Site ID: #21

Location:
Vancouver, Clark County

Contact:
Paul Skyllingstad, project manager
(360) 407-6949

Status: Active Get definitions of Status terminology


ADDITIONAL INFO

Alcoa Joint Aquatic Resources Permit Applications (JARPA) (pdf)

Alcoa Vancouver Focus Sheet (pdf)

Progress Report (html)

Final Enforcement Order (pdf)

Updated schedule in process


SITE NEWS

Alcoa News Releases:
12/16/2008 - Dredging underway at former Alcoa aluminum smelter

Ecology News Releases:
9/10/2008 - Agreement on consent decree reached; public comment period underway

6/5/2008 - Prep work for river sediment cleanup at Alcoa subject of meeting

2/15/2008 - Alcoa submits federal application for environmental dredging at Vancouver site

12/06/2007 - Agreement reached on river cleanup strategy for Vancouver's Alcoa site

11/09/2007 - Ecology, Alcoa announce accelerated cleanup of Vancouver site

Media Contact:
Kim Schmanke, Ecology communications
(360) 407-6239